Timeefficiency of constructionwork in a developing country
Linköping University, Department of Science and Technology, Communications and Transport Systems. Linköping University, The Institute of Technology.
2015 (English)Independent thesis Basic level (university diploma), 20 credits / 30 HE creditsStudent thesisAlternative title
Tidseffektivisering av byggarbete i Uland (Swedish)
Abstract [sv]

Att arbeta tidseffektivt, strukturerat och inte spilla tid är viktiga faktorer vid ett byggarbete. Tid är pengar och desto längre tid ett arbete tar, desto mer pengar kostar det. Enligt teorin finns det ett flertal faktorer som påverkar effektiviteten på en byggarbetsplats. Några av dessa faktorer är struktur- och tidplaner, arbetsberedningar, planeringsmöten, metodförbättring och att identifiera mål. I Sverige arbetar man efter dessa faktorer på de flesta byggen, men i ett U-land är inte byggnationen lika utvecklad och man arbetar ofta dag för dag. Ett land som har problem med effektiviteten på arbetsplatsen är det fattiga landet Filippinerna i Asien.

Under en volontärarbetsresa till Filippinerna observerades brister och tidsproblem vid byggnationen. Volontärarbetet ägde rum i en liten by vid namn Los Amigos utanför staden Davao. Arbetet gick ut på att bygga upp och renovera bostäder och området runtom byggnaderna åt rullstolsburna människor som inte har råd med ett eget hem. Vid sidan om volontärarbetsplatsen fanns även en byggarbetsplats som observerades under resan. Byggarbetsplatsen bestod av en basketplan.

Denna studie syftar till att observera byggarbetet i Filippinerna för att identifiera problem med byggarbetet och effektiviteten på arbetsplatsen. Genom iakttagelser och intervju med en arbetsledare i byn Los Amigos har de olika tidsproblemen reflekterats och diskuterats. Utifrån de teoretiska referensramarna och med hänsyn till kulturen i landet har förbättringsförslag arbetats fram.

Rapporten avslutas med två avsnitt som beskriver hur man kan arbeta mer tidseffektivt, strukturerat och undvika tidsförluster. Det ena avsnittet handlar om byggarbetet på volontärarbetsplatsen och den andra om arbetet på basketplanen som byggs i samma område. Arbetsplatserna är av helt olika karaktär och olika förbättringsförslag har därmed arbetats fram.

Abstract [en]

To work time efficient, structured and to not waste time are important factors at a construction work. Time is money and the more time a job takes the more money it costs. In theory, there are several factors that affect the efficiency at a construction site. Some of these factors are structural and schedules, work preparation, planning, method improvement and to identify targets. Most of these factors are used in construction work in Sweden, but the construction is not as developed in a developing country and they often work day by day. A country that has problems with efficiency in the workplace is the poor country Philippines in Asia.

During a volunteer work trip to the Philippines was the deficiencies and timing problems during construction observed. Volunteer work took place in a small village called Los Amigos outside the town of Davao. The work was to build and renovate homes and the area around the buildings for wheelchair people who can’t afford their own homes. Besides the volunteer work was a construction site that was observed during the trip. The construction site is made up of a basketball court.

This study aims to observe the construction work in the Philippines to identify problems with building work and efficiency in the workplace. Through observations and an interview with a supervisor in the village of Los Amigos have the different time problems been reflected and discussed. Based on the theoretical frameworks and taking into account the culture of the country have improvement proposals been worked out.

The report ends with two sections that describe how to work more time-efficient, structured and avoid time losses. One section deals with the construction work on volunteer work and the other for a work on the basketball court built in the same area. The workplaces are of completely different character and various improvement proposals have thus been drawn up.

Place, publisher, year, edition, pages
2015. , 0 p.
National Category
Construction Management
Identifiers
URN: urn:nbn:se:liu:diva-119963ISRN: LiU-ITN-TEK-G--15/043--SEOAI: oai:DiVA.org:liu-119963DiVA: diva2:838715
Subject / course
Civil Engineering
Uppsok
Technology
Supervisors
Examiners
Available from: 2015-07-01 Created: 2015-07-01 Last updated: 2015-07-01Bibliographically approved

Open Access in DiVA

fulltext(2068 kB)126 downloads
File information
File name FULLTEXT01.pdfFile size 2068 kBChecksum SHA-512
538af7c4caa82e9aea5de70d6b0caad628a16b547e628533db070d7cd62078d5b8ca9c6e32d014a0e0036d4792da67517297454448f27f0e7ddca8359cd06ddf
Type fulltextMimetype application/pdf

Search in DiVA

By author/editor
Bruce, Linnéa
By organisation
Communications and Transport SystemsThe Institute of Technology
Construction Management

Search outside of DiVA

GoogleGoogle Scholar
Total: 126 downloads
The number of downloads is the sum of all downloads of full texts. It may include eg previous versions that are now no longer available

urn-nbn

Altmetric score

urn-nbn
Total: 103 hits
CiteExportLink to record
Permanent link

Direct link
Cite
Citation style
  • apa
  • harvard1
  • ieee
  • modern-language-association-8th-edition
  • vancouver
  • oxford
  • Other style
More styles
Language
  • de-DE
  • en-GB
  • en-US
  • fi-FI
  • nn-NO
  • nn-NB
  • sv-SE
  • Other locale
More languages
Output format
  • html
  • text
  • asciidoc
  • rtf