Effektivisering av hantering och insamling av mjukplast på byggarbetsplatser - en tids- och flödesanalys med koppling till APD-planering
2026 (Swedish)Independent thesis Basic level (degree of Bachelor), 10,5 credits / 16 HE credits
Student thesisAlternative title
Improving the Handling and Collection of Soft Plastic at Construction Sites - A Time and Flow Analysis with Integration into Site Layout Planning (English)
Abstract [sv]
Byggsektorn är en av de största plastkonsumenterna i Sverige och står för cirka 20 procent av landets totala plastanvändning, samtidigt som mindre än en procent av plastavfallet materialåtervinns. Mjukplast i form av emballage utgör en betydande del av detta avfall, men den praktiska hanteringen på byggarbetsplatser präglas ofta av bristande rutiner, ineffektiva flöden och låg sorteringskvalitet. Syftet med denna studie är att undersöka hur mjukplast hanteras i praktiken på byggarbetsplatser, med fokus på arbetsrutiner, avfallsflöden och tidsåtgång från uppkomst till slutlig hantering, samt att identifiera faktorer som påverkar effektiviteten. Datainsamlingen byggde på observationer, tidsstudier samt ostrukturerade och semistrukturerade intervjuer. Insamlad kvalitativ och kvantitativ data analyserades och kopplades till tidigare forskning inom bygglogistik, flödesanalys, källsortering och standardisering av arbete. Resultaten visar att montörer genererar mest mjukplast, främst vid uppackning av vitvaror, och att tre olika arbetssätt tillämpades på arbetsplatsen, dessa är att arbetaren själv bär avfallet hela vägen till containerområdet, att flödet delas upp mellan två arbetare vid entréplan samt att avfall kastas via fönster ned till entréplan. Renhetsgraden på den insamlade mjukplasten varierade mellan cirka 95/5 för de två första arbetssätten och 80/20 för det tredje. Tidsstudierna visade att hissväntan och sortering vid containerområdet utgör de mest tidskrävande och variabla momenten, där hissen identifierades som en tydlig flaskhals i avfallsflödet. Slutsatsen är att hanteringen av mjukplast i hög grad styrs av arbetsplatsens layout, tillgång till gemensamma resurser samt ansvarsfördelning och arbetsrutiner. Inget av de observerade arbetssätten är optimalt utan medför en målkonflikt mellan tidseffektivitet och sorteringskvalitet. Studien visar att förbättringspotentialen främst ligger i tydligare ansvarsfördelning och standardiserade rutiner.
Abstract [en]
The construction sector is one of the largest consumers of plastic in Sweden, accounting for approximately 20 percent of the country's total plastic use, while less than one percent of plastic waste is recycled. Soft plastic in the form of packaging constitutes a significant portion of this waste, but practical handling on construction sites is often characterized by inadequate routines, inefficient flows and low sorting quality. The purpose of this study is to investigate how soft plastic is handled in practice on construction sites, focusing on work routines, waste flows and time from generation to final handling, and to identify factors that affect efficiency. Data collection was based on observations, time studies and unstructured and semi-structured interviews. Qualitative and quantitative data collected were analyzed and linked to previous research in construction logistics, flow analysis, source sorting and standardization of work. The results show that fitters generate the most soft plastic, mainly when unpacking white goods, and that three different working methods were applied at the workplace, these are that the worker carries the waste all the way to the container area, that the flow is divided between two workers at the entrance level and that waste is thrown through windows down to the entrance level. The purity of the collected soft plastic varied between approximately 95/5 for the first two working methods and 80/20 for the third. The time studies showed that waiting for the elevator and sorting at the container area constitute the most time-consuming and variable moments, where the elevator was identified as a clear bottleneck in the waste flow. The conclusion is that the handling of soft plastic is largely controlled by the layout of the workplace, access to shared resources and the division of responsibilities and work routines. None of the observed working methods is optimal but entails a conflict of goals between time efficiency and sorting quality. The study shows that the potential for improvement lies primarily in clearer division of responsibilities and standardized routines.
Place, publisher, year, edition, pages
2026. , p. 52
Keywords [en]
Soft plastic waste, Time study, Observational study, Waste management, Waste sorting quality
Keywords [sv]
Mjukplastavfall, Tidsstudier, Observationsstudie, Avfallshantering, Sorteringskvalitet
National Category
Construction Management
Identifiers
URN: urn:nbn:se:liu:diva-224790ISRN: LiU-ITN-TEK-G--26/022--SEOAI: oai:DiVA.org:liu-224790DiVA, id: diva2:2070677
External cooperation
Ragn-Sells Stockholm
Subject / course
Civil Engineering
Supervisors
Examiners
2026-06-122026-06-122026-06-12Bibliographically approved